UARP Crane Controls Upgrade
   

Closed
1
Q&A
UARP Crane Controls Upgrade
Sacramento Municipal Utility District
Loading...
Posted On:  9 May 2022
Open for bidding on:  9 May 2022
Response Deadline:  6 Jul 2022 2:00 PM PDT
Not Interested
 | 
Share:
Opportunity Amount: $1M to $5M USD
Contract Length: 36 months
Response Deadline: 6 Jul 2022 2:00 PM PDT
(Closed for response)
Award Date: 30 Sep 2022
Posting ID: 12980461(Doc3465196496)
Posting Type: Request for Information
Public Posting: https://discovery.ariba.com/rfx/12980461
Product and Service Categories 
  • Power monitoring or control systems
Ship-to or Service Locations
Posting Summary
PROPOSAL DOCUMENTS WILL BE AVAILABLE TO DOWNLOAD ON 5/13/22

Contractor shall design, furnish, deliver and test complete digitally based control systems, adjustable frequency AC drives, AC motors, necessary motor mounts, hoist load monitoring systems, remote controls with communications and brake system upgrades to provide for fully functional control systems for gantry cranes located at Loon Lake, Robbs Peak, Jaybird, Camino and White Rock powerhouses in SMUD’s Upper American River Project.  

SMUD will provide mechanical and electrical installation, interconnection conduits, interconnection cabling and applicable 480VAC, 60 Hz power feeds.  

Existing cab mount manual control levers and switches will be removed (provide remote controls only).  

Contractor shall provide drawings, documentation and training necessary for maintenance and operation of the system by SMUD.  

Surplus equipment to remain the property of SMUD.  

Contractor shall supply installation support, start-up commissioning, load test certification support and training.  

SMUD intends to award one or more contracts.